START DATE: November 10, 2001 CONTRACT COMPLETION DATE: May 15, 2002 SCOPE OF WORK: Construction of a new 3060 square foot combined office warehouse building. PEMB, concrete slab on grade, masonry, metal stud interior partitions, gypsum board, cabinets, windows, suspended acoustical ceiling, doors, electrical, HVAC, plumbing, fire sprinkler, fire alarm, data base conduit & wiring. Special Construction R-43 insulation for Roof and Walls. |
Project Site
Loading Dock Site
Pothole For Water Supply Water
Tap & Main Valve
Water Supply Line
Main Water Supply Valve
Sewer Connection @ Main Sewer
Cleanout @ Main
Sewer Line
Sewer Connection For Cleanout
Sewer Cleanout @ Building
Toilet & Sink Drains
Toilet Sewer Lines
Water Supply Valve
Common Trench for Elec., Telephone, & Water
Perimeter Footings
Perimeter Footings
Rebar in Masonry Footings
Rebar in Masonry Footings
Rebar in Block Loading Dock
Importing of RO Water for Masonry Completed
Block Loading Dock
Placement of 10 Mil Poly in Footers
Poly in Column Footings
Forms & Compacted Base
Pouring of Concrete
Building Slab
Placing Curing Blankets
Kelly Penrod Placing First Column
Building Layout
Placing First Beam
Placing High/Low Roof Beam
Framing of Windows
Framing of Windows & Door Way
Unused Vent Framing
Heavy Iron And Purlins in Place West View
Heavy Iron And Purlins in Place South Views
Infrastructure Fascia Trim
High Foundation Wall
Portal Frame Attachment
Attaching of Wall Panels
Layout of Interior Walls
Epoxy Anchor Bolts
Interior Wall Framing
High Rider System
Purlin Cap and High Rider System
Dry pack in Front Porch Area
Anchor Bolt Placement
Framed Interior Walls
Framing of Windows
Girders & Purlins In Place
Wood Trim on Beams For Drywall Placement Framing of Doors
& Windows @ Loading Dock
Roof Purlins
Exterior Wall Framing
Wall Panel Connection
Alex Lopez Cutting Wall Panels
Placing Soffet Panels in Font Porch Area
Completed Wall Panels
Placing Roof Insulation & Panels
South Elevation
Thrust Block Under Slab
Coring For Fire Supply Riser
Under-Slab Fire Supply Line Ductile
Connection For Fire Supply
Fire Supply Line
Dave Moore Compacting Fire Supply Line
Pressure Tested For 2 Hours @ 150 PSI Water Supply
@ Backflow Preventer
Jimmy Clair With Completed Backflow Preventer Backflow
Preventer Ready For Cement
Irrigation Line
Warehouse HVAC Unit
Office HVAC Duct Work Warehouse
HVAC Unit
Office HVAC System Bathroom
Exhaust Fans
Exhaust Vent Penetration to Exterior of Building Rough In Plumbing
For Water Heater & Mop Sink
Completed Bathroom Rough In Plumbing Rough
in Bathroom Plumbing
East Wall Insulation & Framing South
Wall Insulation & Framing
Firewall & High Wall Steel Framing
Wall Insulation & Electrical Conduits
Roof & Wall Insulation
Plywood Skin in Warehouse
Un-taped Drywall in Hallway
Hanging Suspended Acoustical Ceiling Grid
Bathroom Cabinet Greg Mayhan Placing Chair
Rail Steve Lewis Hanging an Exterior Door
Installation of Chair Rail in Exec. Director’s Office
Fire Wall in Warehouse
High/Low Roof Wall
Jason Hoehn Installing Interior Horn/Strobe
Shawn Lovato Connecting Water Flow Switch Installation
of Suspended Acoustical Ceiling
Fire Alarm Circuit Board Shawn
Lovato & Jason Hoehn Testing Fire Alarm System
Jason Hoehn Installing Exterior Horn/Strobe Jerome
Cardenas Hanging Telephone Backboard
Data & Voice Cabling
Data & Voice Punch box
Exhaust Fan & Hood
Main Breaker & A/C Unit
Bump Stop Installation
Dust Storm
Finished Bathroom
Water Heater
Telephone Conduit @ Pedestal With Thrust Block
East Elevation
North Elevation
South Elevation
November 28, 2001
May 14, 2002