Chalone Creek
Fire Cache Building- 1500 sf.
Dormitory - 4000 sf.
Trails Building
- 3000 sf.
Site Utilities.
Chalone Creek Support Area, Pinnacles, CA.

 

11-11-02 to 11-18-2002

  

Asphalt Grinding Machine Removing Asphalt for 6” Water Loop

 

  

Steve Layton Grooving Pipe for Temp Water By-Pass                          Ground Up Asphalt Roadway

 

  

K. Nickerson Excavator on Site                                            Temp 3” Line Completed

  

Temporary 3” Water Line In Place                                    Temporary Water Tanks, During

    Refinishing Of Main Tank

 

  

Oak Tree Removed, Future Dorm Site                               C. Cardenas Capping Water Main,

So Dorm Pad Can Be Cut

 

  

Capped Main                                     K. Nickerson Compacting Keyway on New Entrance

 

  

Excavation over Pad, Started                                        Steve Layton Clearing Tree Brush

 

  

C. Cardenas Cut Main Tree Trunk                                                  46” Across, Red Oak

 

  

C. Cardenas with New Stihl                                      S. Layton Pile of Wood from 2 Oaks

 

  

Loading Hi-Side with Tree Roots & Brush

 

November 25 to December 5, 2002

  

Old LP Gas Pipe Removed From Trailer Pad              C. Cardenas Installing New Water Line for Trailers

 

  

Sheep’s Foot Compacting Trails Pad                                            Leveling Fill Trails Pad

 

  

       Smooth Drum on Trails Pad                                    Steve Layton Grooming Around Trailers

 

  

                                             Gym at New Location Ready to Be Leveled                                     Finished Fire Cache Pad

 

  

         Completed Moved & Hook-Up Gym & Lab             Looking Across Back of Fire Cache to Entrance Ramp

 

  

Gym Setup on New Location                                              Final Grade on Trails Pad

 

  

                   Placing Fill on Ramp                                         Looking Toward Project from Access Road

 

  

Cameron Cardenas Assembly of Valves                                                  Duplex Pad

 

  

Temp Water Trailer 3” Sag in Top of Bed              Nicholson Scraper Removing Dirt from New Duplex Pad

 

  

Entrance Ramp, Still Needs 12” Culvert                           6” Valve Installed In Tank Line To Site

 

  

Tank Valve with Kicker Installed                                  Placing Kicker on Valve for 6” Loop

 

  

Jimmy Clair & Cameron Cardenas                               New 4” Valve Tie In For Trail Fire Sprinklers

          Pipe + Valve Installers Inc.

 

December 9, 10, 11, 2002

  

Trenching Riser on Trail Building                                    Al Plaxton Compacting Footings

 

  

Fire Cache Chalked Out For Trenching                            Vapor Barrier Spread on Fire Cache

      Cameron Cardenas Pressure Testing Riser

 

  

     Al Plaxton & Cameron Cardenas                              Mc Kibbon Plumbing Installing Waste Lines

In Trails Building

 

  

200 PSI on Sprinkler Riser Fire Cache                                         Waste Lines Installation

 

  

       Cameron Cardenas, Jimmy Clair Testing Riser                                200 PSI - Trails Building

       In Trails Building

 

  

Sand Installed On Fire Cache                                  Vapor Barrier Going Down Over Gravel,

Trails Building

 

  

      Trails Vapor Barrier                                                 C. Cardenas Preparing Fittings

 

  

Leveling Sand in Trails Building                                       Taping Seams on Vapor Barrier

 

  

Trace Wire Installed On 4” Fire Line to Trails Building

 

  

C. Cardenas Assembling 90° D.I. Fitting Fire Line To Trails Building

 

  

#4 Rebar Matt Ready for Dobbies Fire Cache

 

  

Rebar In Footings – Fire Cache

 

December 9, 10 & 11, 2002

  

Trenching Riser on Trail Building                                    Al Plaxton Compacting Footings

 

  

Fire Cache Chalked Out For Trenching                            Vapor Barrier Spread on Fire Cache

   Cameron Cardenas Pressure Testing Riser

 

  

   Al Plaxton & Cameron Cardenas                                Mc Kibbon Plumbing Installing Waste Lines

In Trails Building

 

  

200 PSI on Sprinkler Riser Fire Cache                                         Waste Lines Installation

 

  

       Cameron Cardenas, Jimmy Clair Testing Riser                                    200 PSI - Trails Building

      In Trails Building

 

  

       Sand Installed On Fire Cache                                          Vapor Barrier Going Down Over Gravel,

                Trails Building

 

  

Trails Vapor Barrier                                                 C. Cardenas Preparing Fittings

 

  

Leveling Sand in Trails Building                                       Taping Seams on Vapor Barrier

 

  

Trace Wire Installed On 4” Fire Line to Trails Building

 

  

C. Cardenas Assembling 90° D.I. Fitting Fire Line To Trails Building

 

  

#4 Rebar Matt Ready for Dobbies Fire Cache

 

  

Rebar In Footings – Fire Cache

 

12-23-02 to 1-7-03

  

6” Water Trench, Look Toward Building 300                        C. Cardenas Assembling 225 P.I. Fitting,

Behind Fire Cache

 

  

      Diversion Next To Fire Cache, For Rain Water                      Sand Bagged Area behind Fire Cache

 

  

         Setting Floor Drains, Trails Building                        6” Water Line Heading toward Duplex 101 & 102

 

  

Al Plaxton Vibrating Footings                                           Pouring Footings, Fire Cache

 

  

Pouring Fire Cache Slab                                                    Fire Cache Poured out

 

  

Footers Poured, Trails Building                                   Pouring Slab Trails Building, Plaxton Concrete

 

  

      Pouring Slab Trails Building, Plaxton Concrete                              6” Water Line In front Of Duplex

 

  

6” Water Line In front Of Duplex                                 Al Plaxton Cutting Joint in New Slab

 

  

Al Plaxton Cutting Joint in New Slab                                             Soft Cut Machine

 

  

Joint in New Slab, Final Product                               C. Cardenas Backfilling with Skip Steer

 

  

      C. Cardenas Backfilling with Skip Steer                   Tee & Valve In Front Of Duplex, 22.5” D.I. Fitting

 

  

Looking To 22.5” Valve Assembly                         Looking Toward Duplex 102, 6” Gate Valve

 

Week of 1-13-03

  

Compacting 6” Water Line                                Looking Toward Tank Line Need Breaker Point

 

   

C. Cardenas Bedding Pipe                                6” Lateral – Looking Toward Old Duplex 102

 

  

Looking Toward Tank Line, Hit About 30 FT of DG That Had To Be Broken Up With Breaker Point

 

  

Broken Up Ground in Water Trench                        Mod to High Pressure Waste Line Shorten Up Feed

 

  

Coupler Fitting On 6” Water Pipe                                                 C. Cardenas Back Filling

 

  

     Eric Freeth Reviewing Plans, Trails Unit Plated                              Trench for Culvert under Entrance

 

  

D. Moore, R. Akerstrom Cutting Studs                                         Info on Culvert Pipe

 

  

Undoing Valve, Ready to Remove Hydrant                             C. Cardenas Removing Hydrant

 

  

Removing 2ND Hydrant                                       Removed 6” Barrel Hydrant W/4” Valve

 

Kurt Lanning, Compacting Soil over Culvert, Mark Nicholson Behind

 

Week 1-20-03 to 2-4-03

  

Relocated Hydrant #2                                      Ditch Looking Toward Existing Ductile Iron Pipe

 

   

150-PSI Test on Main Water Line                                     Walls Stood Back Of Trails Building

 

  

Wall’s Stood Back Of Trails Building                                       Ridge Beam for Fire Cache

 

  

Front of Trails Building, Wall’s Stood Plumb & Lined

 

  

  Framing Walls Fire Cache                                  Mike Cardenas Conferring With Head Carpenter,

 Eric Freeth

 

  

     Side Walls Fire Cache Framed                                1st Load GG&E Sand for Bedding Conduit

 

  

Nailing Blocks, Trimmers in Side Walls                                    Walls Stood On Fire Cache

 

  

   Ready To Frame Front Wall                                         Trails Building Shear Panel Installed

 

  

Mike Cardenas Cutting Out Lookers in Gable Trusses                   Hand Trenching Around Existing Utilities

 

  

Trenched & Sand Installed, Main Electric Ditch

 

  

       Trenched & Sand Installed, Main Electric Ditch                       Conduits Installed Toward Main Vault

 

  

  Conduits Installed To Main Vault                                                      Conduit Penetrations

 

  

Conduit Penetrations Inside Of Vault, Ready For Grout                             More Hand Digging

 

  

Rear of Fire ½ Sheared                                                Cameron Cardenas, Eric Freeth,

Installing Shear on Fire Cache

 

  

Framing Complete Trails Building                                                          Picture from Road

 

Week 2-5-03 to 2-13-03

  

Jimmy Clair Grading With New Skid Steer                     Twin Scissor Lifts in Action on Fire Cache

 

  

Electrical Trench toward Comfort Station                              Electrical Penetrations in Vault

 

  

Setting Ridge Beam on Fire Cache                                      Cameron Cardenas, Eric Freeth

 

  

       Ridge Beam Set                                                        Conduits to New Buildings

 

  

   Conduits                                                                   Grouted Into Vault

 

  

Conduit to Comfort Station                                               Grouted Inside Vault

 

  

Grouted Vault

 

Toby Layton Cutting 4” Dia. Pipe To Install New Valve in Water Tank Line

 

Week 2-18-03

Extra Job Installing 4” Gate Valve in Supply Line from Tank

 

Extra Job Installing 4” Gate Valve in Supply Line from Tank

 

Jimmy Clair Painting Overhang, Cameron Cardenas Tending and Driving Lift

 

  

Steve and Toby Layton Installing Fire Sprinklers               A/C Unit Removed, Roof Patched, Dried, In

In Fire Cache                                                                       Building 300

 

  

Removing A/C Unit on Building 300

 

Removing A/C Unit on Building 300

 

View of Project from Entrance

 

Week 2-20-03

  

        Concrete Chipped To Install Termite Shield                                        Termite Shield Installed

 

  

Fire Sprinkler Riser in Trails Maintenance                                 Fire Sprinkler Riser, Fire Cache

 

Test Gauge, Fire Cache

 

  

Vapor Barrier, Fire Cache                                    Power Vault Behind Maintenance Building

 

  

Telephone Duct Behind Building 300                                Telephone Duct behind Fire Cache

 

2-21-03

  

Sprinkler Test                                                      Sprinkler Riser in Trails Building

 

Sprinkler System in Fire Cache

 

  

         Completed Repair on HVAC Roof Removal, Building 300                       Vault Install Behind Building 300

 

  

        Eric Freeth Installing Tar Paper on Fire Cache              Robert Akerstrom Installing Tar Paper on Fire Cache

 

Trench to Maintenance Building

 

Utility Trench with Bedding Sand Behind Building 300

 

2-24-03

  

          LP Gas Tee from Trail and Fire Cache, with Tracer Wire                               LP Riser at Fire Cache

 

  

  LP Gas Riser, Trail Building, With Test Gauge                Trench Line with Bedding Sand, Ready for Backfill

 

  

Trench Line with Marking Tapes                                         30LBS on LP Gas Line Test

 

  

Lines to Maintenance Yard                                         Inside Power Vault, Building 300

 

  

Inside Phone Vault Behind Building 300                                                Fire Cache Dried In

 

Eric Freeth Papering Trails Building

 

Installing Paper on Trails Roof

 

  

Evaporative Cooler Ducts in Trails Building                    Vapor Barrier Installed On Trails Building

 

Cameron Cardenas Delivering Bedding Sand to Trench Behind Building 300

 

2-25-03

  

Hand-Dug Electric Trench behind Lounge                                    Toby Layton Stocking Roof

 

Stocking Roof

 

  

      Eric Freeth Installing Flashing, Starter Strip,                   Hand-Trenched Line behind Maintenance Office

        And First 4 Rows Of Shingles

 

  

 4” Telephone Line, 11/2” Electric behind Building 300              Electric And Phone Vaults Behind Building 300

 

 

  

Pumping Old Septic Tank                                                      Washing Out Tank

 

Rinsing Tank and Final Pumping For Abandoning

 

2-27-03

  

Rinsing Old Septic Tank and Final Pump                    Punching Holes in Bottom after Lid Removed

 

  

Breaker Point at Work, Side View                                         Spreading Ύ Rock in Old Tank

 

  

Rock Completed                                                                    Start Backfill

 

  

Placing Sealer between Grade Rings behind                   Cameron Cardenas Compacting Around New

Building 300                                                          Vaults behind Building 300

 

  

          Existing Manhole with Completed Bore for Trails Building                            Boring Hole in Progress

 

3-4-03

  

      Sewer Line Installed Into Manhole to Manhole                            Completed Line from Trails Building

 

  

Roof of Trails in Progress                             Completed Grout around Metal Column in Fire Cache

 

  

Saddle Installed On Water Main for Trails                         Cleaning Bored Holes for Epoxy Prior To

    Installing Anchor Bolts at Mud Sill Splices

 

Robert Anderson Removing Limbs from Large Branches

 

  

          Picking up Logs with the 446 Cat Backhoe                100’ Pine, 80’ Boom Lift, Jimmy Clair and Cameron

       Cardenas Topping Tree.         Note: Backhoe Size

 

Robert Akerstrom Removing Brush from Logs

 

3-6-03

  

Tony from Tognetti’s Electric Working on                             Completed Trails Fire Sprinkler Riser

      Trails Sub Panel

 

  

Evap Cooler Duct Work in Trails Building                     Eric Freeth Roofing Back Side of Fire Cache

 

  

36” Diameter Stump from 100’ Tall Pine                                                    Log Pile

 

  

  Digging Out Stump                                                   Jimmy Clair Proud Of His Roots!

 

  

    Had To Use Gradall to Remove Roots from Here                                Hole With Stump Removed,

    Ready to Clean Out Roots

 

3-10-03

  

International, Looking Through Rear Window                    Seal Installed On Bottom of Manhole by Lounge

                                 Of Fire Cache

 

  

Grout Used To Insure Seal                                    Cameron Cardenas, Toby Layton Installing

Grade Ring with Sealer

 

  

6” Sewer Line From New Manhole across                     Completed Manhole by Employee Lounge

       Maintenance Yard

 

  

Looking Across Maintenance Yard                                 Toby Layton Compacting Sewer Line

    From New Manhole

 

  

       Siding Being Installed On Back of Fire Cache              Shoring Box Used For Sewer. We Stepped the Trench

    Later So We did Not Have to Use It.

 

3-18-03

  

Manhole Water Tested                                                        Completed Manhole

 

  

Installing Grout for Grade Ring                                            2nd Manhole, Dorm Duplex

 

Grouting For Ring

 

  

Hook-up Hole in Existing Manhole                                6” Line Installed In Existing Manhole

Behind Comfort Station

 

  

     Ready to Seal New Penetration                             Cameron Cardenas Backfilling New Sewer Line

from Dorm Duplex

 

3-26-03

  

Sewer Trench to Dorm Duplex Completed,                                     Utilities in Trails Ceiling

Groomed Back to Nature

 

  

      Finished Siding on Fire Cache                                     Robert Akerstrom and Cameron Cardenas

Installing Siding on Trails Building

 

  

Trails Building Front Door Hung with Trim                    Eric Freeth Installing Man Door on Fire Cache

 

  

Trails Building with Completed Siding                            Jimmy Clair Caulking Fire Cache Siding

 

  

         Eric Freeth Installing Wainscot in Fire Cache                       Steve Lewis Installing Interior Door Frame

 

4-10-03

  

       Robert Kramer of Apple Valley Communications               Jimmy Clair Caulking Wainscot in Fire Cache

Working on Alarm System

 

  

Eric Freeth Hanging Drywall                                    Last Board to Hang In Trails Building

 

  

     Sealed Green Board in Restroom                             Jimmy Clair Painting Back Of Fire Cache

 

  

    John Simons Installing First Coat of Drywall Mud                              Joints Taped In Trails Building

 

  

View from Levee Road                                 Jimmy Clair Continuing To Paint Rear of Fire Cache

 

4-14-03

  

Eric Freeth Building Door Frames                       Cameron Cardenas Cutting, Painting on Wainscot

 

  

Plastic Installed Over Doors Help Dry Mud                  Installing Tongue and Groove on Garage Doors

 

  

       Garage Door Tongue And Groove Installation                                         Completed Door

 

Installing Hinged, Doors Paired Up

 

  

Eric Freeth Installing Hinges                                    Doors Being Fabricated In Fire Cache

 

4-22-03

  

 Nicholson Patching Trench Line in Maintenance Yard                                  Final Rolling Of Patch

 

  

     Removing Asphalt on Road Next To Fire Cache                  Jimmy Clair Painting Interior of Trails Building

 

  

       Painting Door Trim                                                 Jimmy Clair Painting Shop Doors

 

  

Installing First Pair of Doors on Fire Cache                               Fire Cache Stoop Ready to Pour

 

Eric Freeth With First Set of Completed Doors

 

5-1-03

  

  Fire Cache Stoop Poured                                             FAU Behind Building 300 Poured

  R/A & Feed Holes Cut In Building

 

  

     Eric Freeth Finishing First Sidewalk Pour on Trails              Sidewalk Return around Rear of Trails Building

 

  

 Jimmy Clair Installing Back Rod and                                        Formed Sidewalk In Front Of Trails.

Polyurethane on Fire Cache Windows                                                Base Being Installed

 

  

Robert Akerstrom Grooming Around Tree                         Front Sidewalk Ready for Wire Mesh

 

Cameron Cardenas Finishing Front Sidewalk

 

5-8-03

  

Relocation of 6” Gate Valve on Feed to Park

 

  

Relocation of 6” Gate Valve on Feed to Park

 

  

Trench Line of Rerouted 2” Conduit to Pump House       Rob Hill Doing CTE Compaction Test on Dorm Pad

 

  

Completed Dorm Pad                                       Jimmy Clair & Cameron Cardenas Applying

   First Coating to Trails Building Floor

 

5-21-03

  

Trenching For Duplex Footing, Jimmy Clair on Hoe, Robert Akerstrom on Shovel

 

  

     Nicholson Engineering Compacting Entrance              Eric Freeth and Cameron Cardenas Forming Duplex

 

  

Upper Area Trenched On Dorm                                Robert Akerstrom Checking Grade On

Footing At Lower Area of Dorm

 

Kurt Lanning from Nicholson Engineering Grading Entrance to Housing

 

6-3-03

  

Cameron Cardenas Forming Duplex                                         New Culvert under Entrance

 

  

Bottom Rebar Ties Ready for Dobbies                         Robert Akerstrom Grooming Dorm Footing

 

  

      FINE TRUCKS!                                        Nicholson Grading Base in Trails Parking Lot

 

6-4-03

  

Beginning To Remove Old Float Control Valve            Robert Akerstrom Harnessed and Entering Tank

     To Undo Bottom Bolts On Valve

 

  

Robert Akerstrom Entering Tank                                                          Valve Removed

 

  

New Valve Completed                                      Steel Work Completed In Duplex Footings

 

  

24” Spacing on Duplex Uprights                                        20” Wide Footing on Duplex

 

Final Grade Base in Parking Lot

 

6-5-03

  

  First Truck for Base of Footers                                     Coordinator Herb Wosencroft Watching

   Start of Footing Pour

 

  

       Setting Column Base                                            Eric Freeth Finishing Top of Footing

 

  

CTE Tech Checking Slump and Cylinders                      Cameron Cardenas Finishing Duplex Footing

 

  

      Cameron Cardenas Completing Duplex Footing                          Cutting Keyway into Top of Footings

 

  

      Keyway Cut Into Top Of Footing                             Pour On Footing Complete. Eric Freeth And

   Cameron Cardenas Finishing Last Of Footings

 

6-9-03

  

   Dorm Pad With Footer Trenched                               Al Plaxton’s Crew Getting Ready with Forms

 

  

Inside Plywood Panels Being Installed On Duplex

 

  

Duplex, Looking East                                                 Outside Forms Installed On Dorm

 

  

        Installing Steel Uprights on Dorm at 24” O.C.                               Ready To Pump Duplex Walls

 

  

          Cameron Cardenas Doing Final Prep For Pour on Duplex                               Duplex, Looking West

 

6-17-03

  

  C & C Concrete Pumping Set-up                               Al and Eddy Plaxton Help Finish Stem Walls

 

  

         Eric Freeth Finishing Stem Walls on Duplex                                    Mike Cardenas Guiding Hose,

Robert Akerstrom Running Vibrator

 

  

     Center Piers on Duplex Poured and Stirrups Set                                   Setting Up To Pour Dorm

 

  

Preparing To Pour Dorm                                                    Al Plaxton Running Hose

 

  

Finishing Top of Dorm Stem Wall                                  First Pass of Concrete around Dorm

 

  

       Upper Level of Dorm with Stem Wall Floated                                Troweling Dorm Stem Wall

 

  

Al Plaxton Filling Piers on Dorm                                      Mike Cardenas Assisting In The

Finishing Of Stem Walls

 

  

Front of Dorm Stem Walls Stripped                                       East Side of Dorm Stem Wall


Garage Openings on Duplex

 

Looking East on Back Side of Duplex

 

6-18-03

  

        Skid Steer on Ramp, Used To                                                    Skid Steer at Work

Drive Unit into Complex

 

  

     Filling and Compacting Duplex Front Porch Area                        Skid Steer Moving Dirt inside Duplex

 

  

     Dave Moore Compacting and Robert Akerstrom                     Two Stem Walls Finished Inside Duplex

        Spreading Dirt inside Duplex

 

Inside View of Dorm Stem Walls before Backfilling and Compaction

 

Looking At East Side of Dorm Stem Wall

 

6-19-03

  

Backfilling Inside of Dorm Walls

 

  

        Working on 2nd Level, Dorm                                      Completed Inside Stem Walls, Duplex

 

  

        Over-all View of Work on Dorm Backfilling                                Dave Moore Leveling Fill, Dorm

 

  

       Eric Freeth And R. Akerstrom                                                    Dorm Fill ½ Done

Installing Termite Shield

 

Over-all View of Duplex Showing Completed Concrete, Beginning of Framing

 

6-23-03

Duplex Foundation with Termite Shield, Sill Sealer, and Sill Plate Installed

 

  

Sub Floor Beams Installed On Duplex                           Robert Akerstrom Sealing around Anchor Bolts

 

  

  Eric Freeth Installing Sill Sealer                                    Cameron Caedenas and Dave Moore

Bedding Duplex Sewer Pipe

 

  

Center Connection of Duplex Sewer                                 Duplex Sewer Line Passing Through

  Sleeve in Foundation

 

  

   Dave Moore and Jimmy Clair                                  3 Sewer Clean-outs In Front of Duplex

Trenching To Manhole

 

3,200 LBS of Stump Being Hauled Away From Site

 

6-25-03

Eric Freeth and R. Akerstrom Working on Dorm’s Sub Floor Beam

 

  

Completed Sewer Lines On Duplex.                             Eric Freeth Inspecting Sub Floor Work

 

  

Lumber Delivered For Dorm and Duplex                             Jimmy Clair and Dave Moore Coating

     Duplex Walls with Damp- Proofing

 

  

Back Duplex Wall Coated. Note Dirt Pile!                                     4” Water Main to Dorm

 

  

Dave Moore Compacting Entrance                                Completed Sub Floor Joist On Duplex

 To Duplex Garages

 

Installing Sub Floor Joist on Dorm. Damp-Proofing Completed

 

7-8-03

  

      Robert Akerstrom Working on                                      Cameron Cardenas Installing 4” Water

Sewer Line from Dorm                                                         Main behind Duplex

 

Mike Cardenas Moving Dirt for Sewer Line

 

  

Sewer Line from Dorm                                                    Dorm Line into Manhole

 

  

Dorm Sewer Line

 

  

Backfilled Clean-out By Dorm Kitchen                                 Dorm Clean-out, Upper Level

 

7-14-03

  

Dave Moore Compacting Fill Next To Dorm                      Sheeting Duplex, Floor Insulation Installed

 

  

Plumbing Installed On Duplex Subfloor                                Double Check-Valve Water Meter,

 Curb Stop behind Duplex

 

  

   Meters Hooked Up To Water Main with 1” Saddle                          Cameron Cardenas Sheeting

Upper-Level Dormitory Floor

 

  

Lower Dormitory Subfloor Insulated                              J & E Mechanical Fabricating Continuous Rain

       Gutters for Fire Cache & Maintenance Buildings

 

Installing Rain Gutters on Fire Cache (J & E Mechanical)

 

7-29-03

  

Nickleson Engineering Grading Around Duplex              Completed Backfill around Handicap on Duplex

 

  

Cutting Swale around Side of Duplex                                   Upper Rooms Framed On Dorm

 

  

Cameron Cardenas Completing Sheeting                            Dave Moore and Robert Akerstrom

On Lower Level of Dormitory                                          Framing Upper-Level Walls

 

  

Rear of Duplex Walls with Shear Panel                              Swale Cut on East Corner of Duplex

 

  

1 Ό”  Water Meter and Curb Stop to Dormitory                 2 ½” Electrical Ducts to Vault Behind Duplex

 

8-7-03

  

        LP Gas Line and Phone Conduit from Dorm                                LP Gads Line and Phone Line

  Going Around Electrical Box

 

  

Marking Tape Installed In Utility Trench                     Electrical Ducts Terminated Behind Trailer Spaces

 

  

Trusses Loaded On Front of Dorm                                 Conduits Terminated Behind Duplex

 

  

     Electrical and Gas Lines Being Readied                       LP Line with Tracer Wire Installed Behind Dorm

For Installation, Eastern Duplex

 

Trusses Installed On Dorm

 

8-14-03

  

Robert Akerstrom Installing Grout                                    Electric Vault Housing with Future

Between Top Ring and Vault                                             Dorm Line and 2 Stubs Out

 

  

    Cameron Cardenas Working On Dorm Overhang                            Cameron Nailing Off Shear Panel

      on Gable Truss for Duplex

 

  

Looking At Back Of Duplex, East Gable Stood              Completed Framing, Viewed From Rear of Dorm

 

  

Eric Freeth and Cameron Cardenas Installing First Run of Plywood on Back of Duplex

 

 

  

Front of Duplex Trusses Stood                                      Looking at Dorm from Level Road

 

8-27-03

  

Fire Sprinkler System at 210 PSI                                    Duplex Riser Holding at 210 PSI

 

Dorm Riser at 210 PSI

 

9-3-03

  

BCS Mechanical Installing Duct in Duplex                             Dorm Roof Dried In and Stocked

 

  

   Tony (Tognetti’s Electrical) Wiring Kitchen in Dorm                          Duplex Entrance on the H/C Unit

 

  

      Dave Moore Drying In Duplex                                Cameron and Eric Framing Drops In Kitchen

 

  

     Switch Gear Pad behind Duplex Ready for Pour                                      LP Pad Ready to Pour

 

9-8-03

  

Future Dorm 2 1/2” Line Installed

 

  

Future Dorm 2 1/2” Line Installed

 

Looking at West Side of Dorm

 

  

  Looking Along East Side of Dorm                                             Duplex Entry Ready for Base

 

9-9-03

  

       Installing Base Duplex Apron                                   Forms Set Base Install, Duplex Entrance

 

  

Installing Base, H/C Duplex Entrance                               Dave Moore Installing Window Trim

 

  

Working on Dorm Window Trim                                       Al Plaxton Showing Us His Stoop

 

  

Duplex Rear Stoop Poured                                               Installing Base Dorm Patio

 

Garage and Apron Poured on Duplex

 

Cameron Cardenas Running Eave Metal and First 5 Rows of Shingles from Man Basket

 

11-5-03

  

Zzzzzzzz                                                          Western Cabinets and Counters,

      Working on Dorm Kitchen

 

  

Headquarters Kitchen Cabinets completed                                   Tony from Tognetti Electric

      Ready to Pull Wire in Vault

 

  

Spools of Wire for Underground                                       Jambs and Casings Masked Off

     Ready For Painting of 2nd Color

 

  

Duplex 2 Kitchen Cabinets                             Jimmy Clair Standing Window Casing in Duplex

 

  

Tognetti Electric Installing New Switch Gear for Maintenance Yard,

JRCCI Gradal Being Used

 

11-20-03

  

         Floor Store Installing Vinyl                                    Dave McKibbin Installing Sink in 2nd Duplex

       In Headquarters Kitchen Unit

 

  

 Marta Cardenas Sanding 2nd Coat in Dorm                     Cameron Cardenas Standing Casing in Dorm

 

  

     Forrest Anderson Standing Jamb, Second Coat                               Jimmy Clair Painting In Dorm

 

  

Access Grill Installed On Dorm,                                     Front Dorm Windows Masked Off

   JRCCI Fabricated

 

  

     Looking Down Side of Dorm,                                    Dorm Kitchen Cabinets Being Installed

Windows Masked Off